I-25/PASEO PROJECT SWITCHES TO NIGHTTIME WORK

 

CREWS ON THE I-25 / PASEO PROJECT WILL START WORKING AT NIGHT TO MAKE UP FOR THE LOST TIME DUE TO THE RECENT STORM THAT PASSED THROUGH THE STATE. AS OF MONDAY, NOVEMBER 25TH, WORK ON SAN ANTONIO WILL GO FROM 9-PM UNTIL 5-AM.

SAN ANTONIO WILL BE REDUCED TO ONE LANE IN EACH DIRECTION AT I-25 THROUGH WEDNESDAY MORNING.

CREWS ARE NOT SCHEDULED TO WORK ON THURSDAY IN OBSERVANCE OF THANKSGIVING. WORK WILL RESUME ON FRIDAY.